Project Engineer Co-op · Smurfit Westrock · West Point, VA · Aug to Dec 2025

Paper mill projects

Five months on the engineering team of a working pulp and paper mill. Most of my work sat on the maintenance side: safety tooling, structural repair, contractor jobs and water reuse, using JD Edwards for scopes of work, shop work tickets and ordering.

The West Point paper mill at sunset
The West Point mill at sunset.

Drag chain conveyor safety jig

Riveting drag-chain conveyor links took three people: one heats the rivet, one holds a sledgehammer against its back, one strikes. The person holding the backing hammer stood in the line of fire.

I designed a steel vise-style jig that holds the link, so the job needs only one person, a torch and a hammer. I modeled and simulated it in SolidWorks, made the shop drawings, and had it built through JD Edwards work tickets.

Under 25 lbSolidWorks simulation and shop drawingsBench-tested prototype~$5,000 a year saved

Wastewater spur line

Primary Clarifier No. 1 used well water for its skimmer box sprays and to dilute the sludge drawn from its bottom. I compared two replacement sources with head-loss and system-curve calculations.

The existing pump feeding Clarifier No. 2 with effluent had enough head for a spur line over to Clarifier No. 1, so one line could serve both uses.

~60,000 gal/day of well water (projected)Head-loss and system-curve analysisPiping isometrics

Recovery boiler emergency stair repair

Corroded channels under two landings made the Recovery Boiler No. 4 emergency stair a safety hazard. I designed the replacement supports and wrote the scope of work for a repair done during normal boiler operation, and co-managed the project with the maintenance engineer.

Lesson learned: a veteran contractor steered me off a jacking-bolt design that added labor. Now I bring experienced people in early.

W8x18 and W6x25 beams, E70XX field weldsHot work and confined space permitsContractor bid and job walkCo-project manager

Rooftop air makeup unit rebuild

I managed the contractors who demolished and rebuilt the air makeup unit fan on the roof of the Paper Machine No. 1 building, coordinating the crane setup, a valve installation and conduit removal.

Mid-job, an existing beam began failing under its own weight and the concrete load. It was shored before work went further, and the rebuild was finished safely.

Contractor managementCrane lift and site preparationField safety

Safety and compliance

I built a lockout/tagout lunch-and-learn on OSHA 29 CFR 1910.147 and the mill's own program, with a training video script, and ran ISO quality-system and recycling compliance rounds across the mill.

25-slide LOTO training3 ISO quality rounds5 recycling rounds, about 11 areas each

More projects at the mill

Beyond the big projects I carried smaller ones in parallel and kept a project list with start and close dates.

  • PM3 roll-handling laser mounts
  • Recovery chloride removal: surveying and screw piles
  • PM2 caustic felt-wash tank and skid
  • PM2 HVAC motor bracket
  • Batch digester horizontal lifeline
  • PM1 roof steam pipe-over-pipe